Fuelled Certified Report

 

Fuelled Certified Report

Print
Location
Location Yard
Yard stored in Floresville Texas
Status
Equipment Still in Operation No
When was equipment last run 2015-08-13
This is approx.
Does the skid have skirting that needs to be removed No
Equipment still connected to piping No
Equipment still welded down to piles No
Equipment on a gravel pad No
Electrical still connected to the equipment No
Have vessels been cleaned out Yes
to be confirmed
Shiploose items Yes
Possibly. to be confirmed
Service
Hours since last major service? If so, how many? approx. 50hrs
We were told that unit has approx. 50hrs of testing time.
Has equipment been preserved? If so, when? No
Site Logistics
Equipment accessibility in yard or work site
Access into work site
Any road use agreement to access site No
Vessel Registrations
Provincial Vessel Registrations AB, BC
All vessels need to be confirmed.
Equipment Appearance
Missing Parts
Some parts may be missing. Some parts may need to be replaced.
Corrosion
Corrosion is present as unit has been sitting in the elements.
Animal Infestation
Overall cleanliness of package
Operator Notes/Interview/Other Comments
Highly engineered package built by Startec. Levelers on trailer are either damaged or not properly deployed so trailer is leaning.